Soil filling activity using truck

" viAct.Ai ensured the site managers were able to better manage the risk of the fill-site not fulfilling the targeted schedule and the ROI would not be impacted by loss of opportunity cost that can result from exceeding the planned timeline.

​Ringo Cheuk - project manager

Problem

  • The progress of filling a large site was a difficult metric to visualize.

  • The delivery of these results were delayed by a considerable amount of time.

  • Current method of manual calculation would take weeks to be summarized. 

  • This arduous process delayed the delivery of actionable intelligence and could jeopardize the schedule of the upcoming construction project.

Solution

  • Detect and track the number, type and utilization rate of every truck that arrived in the fill site in real time. 

  • Prevent possible project delay costs.

  • The site managers were able to better manage the risk of the fill-site not fulfilling the targeted schedule 